[–] Horse@lemmygrad.ml 6 points 4 months ago* (last edited 4 months ago)

Each factory would send quantified indices of production processes such as raw material input, production output, number of absentees, etc. These indices would later feed a statistical analysis program that, running on a mainframe computer in Santiago, would make short-term predictions about the factories' performance and suggest necessary adjustments, which, after discussion in an operations room, would be fed back to the factories. This process occurred at 4 levels: firm, branch, sector, and total.

seems pretty centralized to me dawg