Summer construction season is coming to an end, but not before we tackle our biggest weekend of construction for the region this year. We're calling it our Monster Weekend. Buckle up (literally) because here's what's going down:

A map depicting full closures of State Route 520, Mercer Street on ramps to I-5, Northbound I-405 in Renton, Southbound SR 167 in Kent, and I-5 OVERNIGHTS ONLY near Fife. The map is covered in cute cartoon monsters.

SR 520 CLOSED - highway and trail

-Where: From I-5 in Seattle to 92nd Ave NE in Clyde Hill
-When: 11 p.m. Friday, Sept. 27, to 5 a.m. Monday, Sept. 30
-What: Working on lighting and the fire suppression system under the new Montlake lid over SR 520.

NB I-405 in Renton CLOSED

-Where: From Sunset Boulevard Northeast/Southport Drive (Exit 5) to Coal Creek Parkway SE
-When: 11 p.m. Friday, Sept. 27, to 4 a.m. Monday, Sept. 30.
-What: Shifting northbound traffic onto a new bridge. A signed detour will be available. This work is weather-dependent and may be rescheduled.

SB SR 167 in Kent CLOSED

-Where: From SR 516 to South 27th Street
-When: 11:59 p.m. Friday, Sept. 27, to 4 a.m. Monday, Sept. 30.
-Why: Paving and striping sections of SB SR 167. This work is weather-dependent and may be rescheduled.

Both directions I-5 CLOSED - overnights only!

-Where: Between SR 18 in Federal Way and 54th Ave E in Fife
-When: Overnight Friday, Sept. 27, and Saturday, Sept. 28. NB lanes will close by 10:30 p.m. and SB lanes by 11 p.m. On Saturday, lanes begin opening at 7 a.m. (fully open by 11 a.m.). On Sunday, lanes begin reopening at 8 a.m. (fully open by noon).
-Why: Setting girders for a new overpass crossing I-5.

Mercer Street on-ramps to I-5 CLOSED

-Where: Mercer Street on-ramps to both NB and SB I-5 in Seattle
-When: 10 p.m. Friday, Sept. 27, and 5 a.m. Monday, Sept. 30.
-Why: Paving the ramp and adjacent shoulders.

Some of these closures have detours, but a warning: Detour routes cannot accommodate normal traffic volumes, so try to travel during off-peak hours or, if possible, delay your trip to help minimize backups.

It's been a long summer of road work. You've been patient, and we're grateful for that. We need to get this work done now before we fully enter The Big Gray.

you are viewing a single comment's thread
view the rest of the comments
[-] barkingspiders@infosec.pub 1 points 1 month ago

Here it comes

this post was submitted on 25 Sep 2024
18 points (100.0% liked)

Seattle

1576 readers
3 users here now

A community for news and discussion of Seattle, Washington and the surrounding area

founded 1 year ago
MODERATORS